Feasibility Studies: Technical, Financial, Economic and Institutional
A feasibility study exists to establish whether a project should proceed, which means it must be capable of concluding that it should not. This guide covers the four dimensions of feasibility, what evidence each requires, the sensitivity testing that separates a decision document from a justification, and how to commission one.
By Charmaine Frost, Director and Landfill Gas Specialist

In short
A waste project feasibility study tests four dimensions: technical, whether the proposed solution works on the actual waste; financial, whether it generates a return sufficient to attract capital; economic, whether it delivers net benefit to society; and institutional, whether the organisations involved can deliver and operate it. Each requires distinct evidence. The study’s value depends on the quality of the underlying characterisation data, gathered under ASTM D5231-92 [1], and on whether recovery assumptions reflect achieved rather than nameplate performance, with Tadweer expecting 15 to 20 per cent recovery from highly automated facilities [2].
Key facts
- Feasibility assessment covers four distinct dimensions, technical, financial, economic and institutional, each requiring separate evidence and any one of which can render a project unviable, with contract structures allocating demand and volume risk explicitly [12].
- Technical feasibility rests on composition data gathered under ASTM D5231-92, reapproved 2016, with sample numbers determined by statistical criteria [1].
- Recovery assumptions should use achieved system rates, with Tadweer expecting 15 to 20 per cent recovery from highly automated facilities [2], rather than equipment stage efficiencies of 85 to 99 per cent [3].
- Gate fee differentials drive revenue: Dubai charges AED 550 per tonne for hazardous waste, AED 100 for general and organic and AED 2 for clean inert construction and demolition material [4].
- Feedstock security is the primary commercial risk, and the stated view from Warsan’s operator is that the key to succeeding with any energy-from-waste plant is first securing a reliable fuel supply [5].
- Warsan took eight to ten years to develop and four years to construct, at approximately USD 1 billion, illustrating realistic programme for a major facility [5].
- Abu Dhabi’s waste-to-energy plant operates under a 30-year concession with EWEC procuring the electricity, which fixes the revenue horizon [6].
- Under UAE Federal Law No. 12 of 2018, Article 4 requires competent authorities to prepare waste management plans and Article 19 provides for inter-emirate joint facilities [7].
Plain English — the essentials, in everyday language
Plain English
What a feasibility study is for
A feasibility study answers one question. Should this project proceed?
That means it has to be capable of answering no. A study that cannot reach a negative conclusion is not a feasibility study. It is a justification document.
The four dimensions
Feasibility is not a single test. It is four, and failing any one is enough to stop a project.
Technical feasibility asks whether the proposed solution works on the actual waste, at the actual scale, in the actual conditions.
Financial feasibility asks whether the project generates enough return to attract and repay capital.
Economic feasibility asks whether it delivers net benefit to society, which is a different question from whether it makes money.
Institutional feasibility asks whether the organisations involved can actually deliver it and then run it for decades.
Technical feasibility
This starts with the waste, not the technology.
You need composition data on the actual stream, gathered properly under ASTM D5231-92 [1], across seasons and across the service area.
Then you test whether the technology performs on that composition. A digester needs organic content and low contamination. A thermal plant needs calorific value. A recovery facility needs material worth recovering.
The nameplate trap
The most common technical error is using equipment performance figures as system performance figures.
Individual stages perform well. Ballistic separation reaches 85 to 90 per cent, magnetic separation 95 to 99 per cent, eddy current 90 to 95 per cent [3].
But chain those together on real contaminated waste and system recovery is far lower. Tadweer expects 15 to 20 per cent recovery from highly automated facilities [2].
That gap between 90-plus per cent stage figures and 15 to 20 per cent system recovery is where optimistic feasibility studies fail.
Financial feasibility
The financial case has three parts.
Capital cost, including everything: land, civils, plant, connections, design, and a contingency sized against genuine uncertainty.
Operating cost, including labour, energy, consumables, maintenance, residue disposal and insurance.
Revenue, which for waste facilities usually combines a gate fee with product sales.
Gate fees dominate
For most waste facilities, the gate fee is the revenue, and product sales are secondary.
The differentials are large. Dubai charges AED 550 per tonne for hazardous waste, AED 100 for general and organic waste, and AED 2 for clean inert construction and demolition material [4].
That spread means the waste type a facility accepts matters more to its revenue than almost anything else.
Feedstock security
The single biggest commercial risk is not having the waste.
The operator of Dubai’s Warsan plant put it directly: the key to succeeding with any energy-from-waste plant is first securing a reliable fuel supply, in coordination with local authorities, and the primary challenge is not technical but establishing the relationship with the relevant authority [5].
A facility without a contracted waste supply is a facility with no revenue.
Economic feasibility
Economic appraisal is not the same as financial appraisal.
Financial appraisal counts money flowing to the project. Economic appraisal counts benefits and costs to society, including things nobody pays for directly.
That means avoided landfill capacity, greenhouse gas savings, avoided imported fuel, employment, and disbenefits like traffic and amenity impact.
A project can be economically excellent and financially unviable, which is exactly the case where public support is justified.
Institutional feasibility
The dimension most often skipped, and a common cause of failure.
Does the client have legal power to procure and contract this? Does it have the technical capacity to specify and supervise? Can it manage a contract for 25 or 30 years?
Are the regulatory approvals achievable in the programme assumed? Who operates the facility, and do they exist yet?
Programme reality
Feasibility studies routinely understate how long things take.
Warsan took eight to ten years to develop and four years to construct, at approximately USD 1 billion [5].
Abu Dhabi’s waste-to-energy plant runs on a 30-year concession [6]. These are long-horizon commitments and the study should reflect that.
Sensitivity testing
A single-point answer is not a decision basis.
Test what happens if waste volumes are 20 per cent lower, if composition shifts, if capital cost overruns, if energy prices fall, if the offtake contract is not renewed.
The useful output is which variables the conclusion depends on. Those are the ones to nail down before committing.
Professional layer — engineering, operations & compliance detail (click to expand)
Professional
Purpose and independence
A feasibility study establishes whether a proposed project should proceed, on what basis, and under what conditions. Its defining characteristic is that it must be capable of a negative recommendation.
That requirement has a procurement consequence. Where the party conducting the study stands to benefit from a positive outcome, whether as prospective designer, contractor or operator, the study’s independence is compromised and its conclusions carry correspondingly less weight with lenders and approving authorities.
The study sits between strategic planning and detailed design. It follows integrated waste management planning and characterisation, and precedes procurement and detailed engineering.
Under UAE Federal Law No. 12 of 2018, Article 4 requires competent authorities to prepare waste management plans [7], and a feasibility study is the mechanism by which a plan’s proposals are tested before commitment.
Technical feasibility
Technical assessment begins with the waste, not the technology, because technology selection is a conclusion rather than an input.
The evidence base comprises composition data from characterisation conducted under ASTM D5231-92, reapproved 2016, with sample numbers determined by statistical criteria and load selection randomised over a five to seven day period [1]; quantity data with a defined uncertainty range; seasonal and spatial variation, since a single sampling period cannot characterise temporal and spatial variability simultaneously [8]; and laboratory analysis on representative composites for moisture, calorific value, ash and, where thermal treatment is contemplated, chlorine, using dedicated analytical methods such as the EN/ISO solid recovered fuel standards (verify against the current standard), since ASTM D5231 covers physical composition by manual sorting only.
Technology screening then tests each candidate against that evidence. The questions are whether the process accepts the composition presented, whether it achieves the required output specification on that feedstock, whether the throughput is within demonstrated commercial operating experience, and whether the residues have identified destinations.
Two disciplines separate credible technical assessment from optimistic assessment.
Performance assumptions must be achieved system rates rather than equipment stage efficiencies. Individual stages perform at 85 to 90 per cent for ballistic separation, 95 to 99 per cent for magnetic separation, 90 to 95 per cent for eddy current and 92 to 98 per cent for near-infrared optical sorting [3], but system recovery from municipal waste is far lower, with Tadweer expecting 15 to 20 per cent recovery from highly automated facilities [2]. Inadequate preprocessing reduces sorting precision by as much as 15 to 20 per cent [9], and stage efficiencies are quoted on prepared feedstock.
Reference plant evidence must be specific. The relevant question is what continuous operating hours the specific technology has achieved on comparable feedstock at comparable scale, not whether the process type exists. Waste gasification, pyrolysis and plasma technologies have substantially poorer commercial delivery records than their technical literature suggests, and neither Abu Dhabi nor Dubai selected them for municipal waste, both choosing proven moving grate mass burn [5][6].
Financial feasibility
Financial appraisal establishes whether the project generates returns sufficient to attract and service capital.
Capital cost estimation should be built up rather than benchmarked, covering land acquisition, site preparation and enabling works, civil and structural works, process plant and equipment, utility connections including grid connection which is frequently a major item for thermal facilities, design and supervision fees, permitting and approvals, financing costs during construction, and contingency sized against assessed uncertainty rather than applied as a conventional percentage.
Operating cost covers labour with realistic staffing and shift patterns, energy, consumables including reagents which are substantial for thermal facilities, maintenance and lifecycle replacement, residue disposal at prevailing gate fees, insurance, and contract management.
Residue disposal cost is frequently understated and is directly determined by gate fee differentials. Dubai charges AED 550 per tonne for hazardous waste, AED 100 for general and organic waste, and AED 2 for clean inert construction and demolition material [4]. A facility generating hazardous residue carries a materially different cost structure from one generating inert residue.
Revenue for waste facilities typically combines gate fee income, which is generally the dominant term, with product revenue from recovered materials, energy or fuel.
Product revenue requires realistic pricing and contracted offtake. Recovered aluminium at USD 800 to 1,500 per tonne is the highest-value common stream [10], but constitutes a small mass fraction. Energy revenue depends on the tariff and its indexation. Material revenue is exposed to commodity price volatility that the project cannot hedge.
Standard outputs are net present value at the appropriate discount rate, internal rate of return, payback period, and debt service coverage ratio where debt financing is assumed.
Economic feasibility
Economic appraisal assesses net benefit to society and answers a different question from financial appraisal.
The distinction matters because waste infrastructure frequently delivers substantial economic benefit while generating insufficient financial return to attract private capital unaided, which is precisely the circumstance justifying public support or availability-based payment structures.
Economic benefits include avoided landfill capacity consumption and its deferred replacement cost; avoided greenhouse gas emissions, with the methane argument central since organic material sent to landfill decomposes and releases methane whereas thermal processing converts that potential methane to carbon dioxide [11]; avoided imported fuel or displaced generation capacity; materials substituting for virgin production; employment and skills; and avoided environmental and health externalities from uncontrolled disposal.
Economic costs include capital and operating resources at economic rather than financial prices, residual environmental impact, and amenity and traffic disbenefit to affected communities.
Conventions require stating the discount rate and its basis, the appraisal period, whether prices are constant or current, and the treatment of transfers such as taxes and subsidies which are not economic costs.
Institutional feasibility
Institutional assessment is the dimension most frequently omitted and a recurring cause of project failure.
The assessment covers legal authority, meaning whether the contracting body has power to procure, contract and pay over the required term; technical capacity to specify, evaluate and supervise; contract management capability over a concession that may run 30 years; regulatory pathway, meaning whether the required approvals are achievable within the assumed programme and from which authority; and operating arrangements, meaning who will operate the facility and whether that entity exists and is capable.
Regulatory attribution requires care in this region because responsibilities have moved. In Abu Dhabi, waste licensing, permitting, vehicle tracking, tariff, sector regulation and inspection transferred from Tadweer to the Environment Agency Abu Dhabi on 29 May 2024, with operational landfill access remaining with Tadweer. In Dubai, waste regulation sits with Dubai Municipality; the current governing law, its implementing regulations and the responsible agency should be verified against the Dubai Legislation Portal or Official Gazette before reliance.
Article 19 of UAE Federal Law No. 12 of 2018 provides for inter-emirate joint facilities [7], which creates an institutional route for catchments crossing emirate boundaries but also introduces the governance question of how such arrangements are contracted and paid for.
The operator’s own stated assessment of the critical factor is institutional rather than technical: the key to succeeding with any energy-from-waste plant is first securing a reliable fuel supply in coordination with local authorities, and the primary challenge is not the technical aspects of the plant but establishing a strong relationship with the relevant authority [5].
Feedstock security
Feedstock security is the commercial risk that determines whether the financial case survives contact with operation, and it warrants separate treatment.
The requirements are a defined catchment, a contracted or otherwise secured supply, and a mechanism addressing shortfall.
Contract structures allocate this risk explicitly. Where the contracting authority takes the entire waste capacity of the plant, revenues are generated through payments which may be structured on an availability basis, with deductions applied where availability and performance criteria are not met [12]. The contracting authority typically bears the risk of supplying waste, either through an availability-based payment structure or by guaranteeing a minimum quantity with liability to compensate for lost gate fee and associated lost power generation on any shortfall [12].
Transferring volume risk to the private party is only practicable where that party has high confidence in volumes through market studies or historical data and can mitigate by filling spare capacity with waste it sources itself; where the government controls collection and disposal of most waste and there is no significant private commercial market, it may be unrealistic for the private party to accept volume risk [12].
Warsan illustrates the structure: contracted for 35 years at 5,500 tonnes per day, representing around 45 per cent of Dubai’s waste, in a one-to-one relationship with Dubai Municipality [5].
Sensitivity and risk
A single-point appraisal is not a decision basis, and sensitivity testing is what converts a model into an assessment.
Parameters warranting testing include waste quantity, tested downward as well as upward; composition shift, particularly where source segregation policy will change the residual stream, as the Shakhbout City two-bin pilot will [2]; capital cost overrun; operating cost, particularly energy and reagents; product and energy prices at the low end of historical ranges; residue disposal cost; availability and downtime; and programme delay.
The output that matters is identification of the variables to which the conclusion is sensitive, because those are the variables requiring measurement or contractual protection before commitment.
Scenario analysis complements parameter sensitivity by testing coherent combinations, since adverse conditions correlate.
Programme and staging
Feasibility studies systematically understate development programme.
Warsan was in development for around ten years, with construction beginning July 2020 and completing July 2024 on a four-year timeline, at approximately USD 1 billion, requiring extensive negotiation and alignment with the municipality [5].
Abu Dhabi’s waste-to-energy plant operates under a 30-year concession with EWEC procuring the electricity, with commercial operations scheduled for 2027 [6].
Those are the realistic reference points for major facility programme in this region, and a feasibility study assuming materially shorter development is unlikely to be delivered.
Staged development merits assessment where demand is growing or uncertain, trading higher unit cost for reduced exposure.
Commissioning a study
For a client commissioning feasibility work, the specification should require:
Independence from prospective delivery parties, stated explicitly.
A defined decision the study will inform and the criteria against which the recommendation will be made.
The characterisation basis, whether existing data is to be used or new work commissioned, and if existing, an assessment of its adequacy including seasonal and spatial coverage.
Performance assumptions stated with their sources, distinguishing measured, reference plant, supplier guarantee and benchmark.
All four feasibility dimensions, with institutional assessment named explicitly rather than assumed.
Sensitivity testing on a specified parameter set with the results presented.
A clear recommendation, with the conditions under which it would change.
The most common deficiency is a study that assesses technical and financial dimensions only, concludes positively, and leaves the institutional and feedstock questions to be discovered during procurement.
Frequently asked questions
What are the four dimensions of feasibility? Technical, financial, economic and institutional. Each requires distinct evidence and failure of any one is sufficient to stop a project.
What is the most common technical error? Using equipment stage efficiencies as system recovery rates. Stages reach 85 to 99 per cent [3] but system recovery from municipal waste is 15 to 20 per cent [2].
How does economic feasibility differ from financial? Financial counts money flowing to the project; economic counts costs and benefits to society including those nobody pays for directly.
What is the biggest commercial risk? Feedstock security. The stated view from Warsan’s operator is that securing a reliable fuel supply comes before everything else [5].
How long does a major facility take to develop? Warsan took eight to ten years to develop and four to construct, at approximately USD 1 billion [5].
References
Show all 12 sources
- ASTM D5231-92 (2016). Standard Test Method for Determination of the Composition of Unprocessed Municipal Solid Waste. Accessed: 7 September 2026.
- The National. Abu Dhabi to significantly cut landfill use in sweeping waste overhaul. 17 July 2026. Accessed: 7 September 2026.
- Waste Technology UK. Best Automatic Waste Sorting Machine Models and Options: comparative separation performance. February 2026. Accessed: 7 September 2026.
- Business Dubai. Waste Management and Recycling Business in Dubai: permitting and gate fee schedule. August 2026. Accessed: 7 September 2026.
- Circular Business Review. Dubai’s Waste-to-Energy Plant to Cut 65 Million Tonnes of CO2 by 2030: interview with Warsan Waste Management Company. Accessed: 7 September 2026.
- Marubeni Corporation. Conclusion of a Concession Agreement for Abu Dhabi Waste-to-Energy Project in the United Arab Emirates. Accessed: 7 September 2026.
- UAE Federal Law No. 12 of 2018 on Integrated Waste Management, Articles 4 and 19. Accessed: 7 September 2026.
- IOP Science. Mastering waste characterisation: seasonal and spatial variation limitations. May 2026. Accessed: 7 September 2026.
- AI Sorting Machine. A Comprehensive Guide to Selecting Waste Sorting Machines: preprocessing effect on sorting precision. Accessed: 7 September 2026.
- Energycle. Eddy Current Separator: How It Works and Selection Guide, recovered aluminium value. July 2026. Accessed: 7 September 2026.
- Khaleej Times. Abu Dhabi’s new waste-to-electricity plant to power 52,000 homes. 15 April 2026. Accessed: 7 September 2026.
- Global Infrastructure Hub. PPP Risk Allocation Tool: Waste to Energy Plant, demand and operating risk allocation. Accessed: 7 September 2026.
Related articles
- Financial modelling
- Waste characterisation studies
- Waste flow modelling
- Procurement and contracting models
- Facility siting criteria
- Integrated waste management plans
- Environmental impact assessment
- Mass burn incineration
- Waste management in the Gulf context
About this article
Charmaine Frost is a landfill gas and waste-management specialist and a founding director of Qualifrost FZC LLC. Her experience was gained with major UK waste-management companies, covering landfill gas generation and collection systems, environmental monitoring and the practical risks of landfill operations. She holds the NEBOSH International General Certificate and has submitted her final NEBOSH Diploma assessment, with results expected in March–April 2027.
Reviewed by Adrian Frost, Director. Every article is checked against primary sources before publication: legal claims are verified against the instrument itself, and figures against the original dataset.
Published 7 September 2026 · Last reviewed 7 September 2026 · Next review September 2027, or sooner if the law changes.