Waste Flow Modelling: Mass Balance and Sankey Diagrams

A waste flow model tracks every tonne from generation to final destination and makes the inconsistencies visible. This guide covers mass balance construction, how to build a defensible Sankey diagram, the data sources and their reliability, and where models are used to justify decisions they cannot support.

By Charmaine Frost, Director and Landfill Gas Specialist

City at night overlaid with data network lines

In short

Waste flow modelling quantifies the movement of material through a waste system, from generation through collection, treatment and recovery to final disposal, subject to the constraint that mass is conserved. The Sankey diagram is the standard visualisation, with band width proportional to tonnage. Models are used for capacity planning, diversion target testing, technology selection and policy appraisal. Their reliability depends entirely on the composition data underlying them, which is why characterisation to ASTM D5231 precedes modelling [1]. Abu Dhabi’s 400,000 tonne per year recovery facility is split 200,000 tonnes municipal and 200,000 commercial and industrial [2].


Key facts

  • Mass balance requires that inputs equal outputs plus accumulation, so every modelled flow must resolve to a destination including losses and residues, with preprocessing quality affecting achieved transfer coefficients by as much as 15 to 20 per cent [7].
  • Composition data underlying flow models is derived by manual sorting under ASTM D5231-92, reapproved 2016, with sample numbers set by statistical criteria [1].
  • Recovery yields must be modelled at realistic rather than nameplate rates: ballistic separation achieves 85 to 90 per cent, magnetic separation 95 to 99 per cent and eddy current 90 to 95 per cent [3].
  • Tadweer expects highly automated recovery facilities to recover 15 to 20 per cent of incoming waste in support of 80 per cent landfill diversion by 2031 [4].
  • Abu Dhabi’s planned greenfield recovery facility is designed for 400,000 tonnes per year, split 200,000 municipal and 200,000 commercial and industrial [2].
  • Dubai’s Warsan waste-to-energy facility processes up to 6,000 tonnes per day and Dubai reported 62 per cent landfill diversion by February 2026 [5].
  • Mass burn bottom ash is roughly 20 to 25 per cent of input mass, which must appear as a modelled output flow rather than disappearing [5].
  • Under UAE Federal Law No. 12 of 2018, Article 23 provides for a national waste database and Article 4 requires competent authorities to prepare waste management plans [6].

Plain English — the essentials, in everyday language

Plain English

What a flow model does

A waste flow model follows material through a system. It starts with what is generated and ends with where every tonne finishes up.

In between it accounts for collection, sorting, treatment, recovery and disposal.

The discipline is that nothing is allowed to vanish. Every tonne entering must leave somewhere, as product, as residue, as emissions or as material still in storage.

Mass balance

That discipline has a name. Mass balance means inputs equal outputs plus accumulation.

It sounds obvious. It is also the most common thing models get wrong.

A recovery facility recovering 20 per cent does not send 80 per cent to landfill. Some leaves as moisture, some as process residue, some as rejects to a different route. If the model does not name each of those, it is not balanced.

The Sankey diagram

A Sankey diagram is the standard way to show a flow model.

Bands run left to right from generation to destination. Band width is proportional to tonnage, so the visual weight matches the actual mass.

Where a stream splits, the band splits, and the branches must sum to the parent. That constraint is what makes a Sankey diagram honest: an unbalanced model produces a diagram that visibly does not add up.

What models are used for

Four main purposes.

Capacity planning: how much treatment capacity is needed, of what type, and when.

Target testing: whether a stated diversion target is achievable given actual composition and realistic recovery rates.

Technology comparison: what different configurations deliver from the same input.

Policy appraisal: what a collection change or a producer responsibility scheme would actually shift.

Where the data comes from

Four sources, in descending order of reliability.

Weighbridge records are the strongest. They are measured, continuous and usually auditable.

Composition studies give the split within a stream, sorted by hand to ASTM D5231 [1].

Facility performance data gives recovery rates, though nameplate figures and achieved figures differ.

Estimates and benchmarks fill the gaps, and should be flagged as estimates wherever used.

The generation figure problem

Most models start with a generation figure, and most generation figures are weaker than they look.

Tonnage delivered to facilities is measured. Tonnage generated is inferred, because material that is self-hauled, informally collected, fly-tipped or handled on site never crosses a weighbridge.

So generation is usually calculated backwards from disposal, which means the model cannot then be used to check disposal against generation. That is circular.

Realistic recovery rates

This is where optimistic models go wrong.

Equipment has a nameplate performance and an achieved performance, and they are not the same.

Ballistic separation runs at 85 to 90 per cent accuracy, magnetic separation at 95 to 99 per cent and eddy current at 90 to 95 per cent [3].

Those are stage efficiencies on prepared feedstock. Chain them together across a real line with real contamination and the overall recovery is lower than multiplying the headline figures suggests.

Tadweer’s expectation of 15 to 20 per cent recovery from highly automated facilities [4] is a realistic system-level figure, and it is well below what stage efficiencies alone would imply.

Residues must appear

Every treatment produces a residue and the model must show it.

Mass burn produces bottom ash at roughly 20 to 25 per cent of input, plus air pollution control residues [5].

Recovery facilities produce rejects. Composting loses mass as carbon dioxide and water. Anaerobic digestion produces digestate and biogas.

A model showing only the recovered product is not a mass balance.

Wet and dry

One technical trap worth knowing.

Waste is delivered wet and much of it is analysed dry. Composting and digestion remove water as well as carbon.

If some flows are wet weight and others dry weight, the balance will not close and the error can be large for organic streams.

State the basis and keep it consistent.

Scenario modelling

The useful output is rarely a single answer. It is a comparison.

A base case models the system as it is. Scenarios then vary one thing at a time: introducing separate food collection, adding thermal capacity, changing a gate fee.

Comparing scenarios against the base case on the same assumptions is what makes the model decision-useful.


Professional layer — engineering, operations & compliance detail (click to expand)

Professional

Purpose and position

Waste flow modelling sits between characterisation and design. Characterisation establishes what the waste is; flow modelling establishes where it goes and what infrastructure is required to send it there.

It is the analytical basis for integrated waste management planning, capacity procurement, diversion target setting and policy appraisal.

Under UAE Federal Law No. 12 of 2018, Article 4 requires competent authorities to prepare waste management plans and Article 23 provides for a national waste database [6], both of which presuppose a quantified understanding of flows.

Mass balance construction

The governing constraint is conservation of mass: for any defined system boundary and time period, inputs equal outputs plus change in accumulation.

Constructing a balance requires four decisions taken explicitly.

System boundary. Whether the model covers a municipality, an emirate, a single facility or a material stream determines what counts as an import or export. Cross-boundary movements must be identified rather than netted off, and the 2021 Implementing Regulation requires cross-emirate transport with GPS tracking [6], which provides a data source for those flows.

Time period. Annual is conventional, but seasonal variation in both generation and composition means an annual average conceals the peak capacity requirement. Where a facility must accommodate peak month rather than average month, the model must resolve to that period.

Mass basis. Wet weight as received is the operational basis and the one weighbridges record. Dry weight is the basis of most composition analysis. Mixing them produces balances that do not close, and the discrepancy is largest for organic-rich streams where moisture may be 60 to 70 per cent.

Accumulation. Material in storage, in stockpiles, in bunkers or accumulated in landfill is a legitimate term and should not be forced to zero.

The practical test of a balance is that every node closes independently, not merely that the system totals reconcile. A model where system inputs equal system outputs while individual facilities do not balance contains offsetting errors.

Node definition and transfer coefficients

Each process in the model is a node with defined inputs, outputs and transfer coefficients.

A transfer coefficient specifies the proportion of an input flow reporting to each output. For a material recovery facility, coefficients are required for each material to each of recovered product, reject and residue.

Coefficients must be sourced and stated. The hierarchy is site-specific measured performance, then comparable facility performance, then supplier guarantee, then published benchmark, and the model should record which applies to each coefficient.

Published stage efficiencies provide a starting point but require derating. Ballistic separation delivers 85 to 90 per cent accuracy at 10 to 20 tonnes per hour, magnetic separation 95 to 99 per cent at 8 to 15 tonnes per hour, eddy current 90 to 95 per cent at 5 to 10 tonnes per hour, and near-infrared optical sorting 92 to 98 per cent at 6 to 10 tonnes per hour [3].

Two derating factors apply. Stage efficiencies are quoted on prepared feedstock, and inadequate preprocessing reduces sorting precision by as much as 15 to 20 per cent [7]. And chained stages compound losses, so a five-stage line does not deliver the product of its individual stage efficiencies applied to a clean stream.

System-level outcomes are correspondingly lower than stage figures imply. Tadweer expects highly automated recovery facilities to recover 15 to 20 per cent of incoming waste [4], which is the system figure appropriate to a flow model rather than the 90-plus per cent stage figures.

Data sources and their reliability

Model quality is bounded by input data quality, and the sources differ materially in reliability.

Weighbridge records provide measured, continuous, auditable tonnage at facility gates and are the strongest available data. They record what arrived, not what was generated.

Composition data derives from manual sorting under ASTM D5231-92, reapproved 2016, with sample numbers determined by statistical criteria and load selection randomised over a five to seven day period [1]. Composition precision propagates directly into every downstream flow, so a model built on a single-season composition study inherits that limitation.

Facility performance data provides transfer coefficients, though achieved performance and nameplate performance diverge, and the divergence is systematic rather than random.

Survey and benchmark data fills gaps and should be identified as such in the model, with sensitivity testing applied to any flow where benchmark data drives a material conclusion.

Regulatory reporting provides consignment-level data where manifest systems operate. Abu Dhabi’s Bolisaty e-manifest system and the GPS tracking requirement for cross-emirate transport under the 2021 Implementing Regulation [6] both generate flow data that models should use in preference to estimation.

The generation estimate problem

The weakest term in most municipal flow models is total generation.

Facilities measure receipts. Generation includes material that never reaches a measured point: self-haul, informal collection and reuse, on-site management, fly-tipping and material diverted directly by producers.

The common approach infers generation from measured disposal plus estimated diversion, which makes generation a derived rather than independent quantity. The model then cannot be used to validate disposal against generation, because the two are not independent.

Where generation must be independently estimated, per capita generation rates applied to population provide a cross-check, though rates vary substantially between residential typologies, and in this region the mix of high-density labour accommodation, villa districts and hospitality zones produces per capita figures that differ by a factor of several between strata.

The honest treatment is to present generation with an explicit uncertainty range and to test whether the model’s conclusions survive across that range.

Residue and loss flows

Models frequently omit or understate the flows that do not represent recovery, and this produces balances that appear to close only because the omission is hidden in a residual term.

Thermal treatment produces bottom ash at roughly 20 to 25 per cent of input mass plus air pollution control residues, both requiring explicit destinations, with bottom ash generally routed to metal recovery and aggregate use and APC residues to hazardous disposal after stabilisation [5].

Biological treatment loses mass as carbon dioxide and water vapour, with composting mass loss substantial and requiring explicit representation rather than appearing as unexplained shrinkage.

Anaerobic digestion outputs are biogas and digestate, with biogas leaving as a gas flow that must still be quantified.

Recovery facilities produce rejects, and reject rate is a first-order determinant of the economics because rejects carry disposal cost at prevailing gate fees.

Moisture is a legitimate loss term where the basis changes between nodes, but it must be stated rather than absorbed.

Sankey construction

The Sankey diagram is the standard visualisation because its geometry enforces the mass balance constraint.

Construction principles: band width is strictly proportional to mass flow, with a stated scale; flows progress in a consistent direction, conventionally left to right from generation to final destination; splits and merges must sum exactly, since a node whose outputs do not sum to its inputs produces a visible discontinuity; and colour should encode material type or destination category consistently.

The diagnostic value is that an unbalanced model produces a diagram that visibly fails to reconcile, which is harder to overlook than an inconsistency buried in a spreadsheet.

Practical conventions: aggregate flows below a threshold into an “other” band rather than rendering unreadably thin bands; annotate absolute tonnages on major flows rather than relying on width alone; and show the base case and each scenario at identical scale so that comparison is visual rather than arithmetic.

For reporting to non-technical audiences, the Sankey is frequently the only output that is actually read, so the labelling and the treatment of residues determine what the audience concludes.

Scenario modelling

Single-point models answer a question that is rarely asked. The decision-relevant output is comparative.

A defensible scenario structure comprises a base case representing the current system, calibrated against measured data; a do-minimum case projecting the base case forward with demographic and economic growth but no intervention; and intervention scenarios each varying a defined set of parameters.

Common intervention scenarios in this region include introduction of separate organic collection, addition of thermal capacity, changes in gate fee differentials, and producer responsibility schemes affecting specific materials.

Two disciplines apply. Vary one thing at a time in the first instance so that the effect is attributable, then combine. And apply the same assumptions across scenarios except for the variable under test, since a scenario comparison in which multiple assumptions differ is not a comparison.

Sensitivity analysis should identify which input parameters materially affect the conclusion. Where a conclusion is sensitive to a benchmark-derived coefficient, that coefficient warrants measurement before the decision is taken.

Common failure modes

Five errors recur and each is detectable.

Recovery rates set at nameplate rather than achieved performance, producing capacity requirements that understate residual disposal need.

Residues omitted or aggregated into a single unexplained term, concealing disposal obligations and their cost.

Wet and dry basis mixed between nodes, producing balances that close only by accident.

Composition applied uniformly across a heterogeneous service area, when spatial variation in paper, metal and textile fractions is statistically significant [8].

Single-season composition applied annually, when seasonal variation in organics can span a 22 to 49 per cent range [8].

Each of these biases the model toward optimism, which is the direction that matters because models are usually commissioned to support a proposal.

Application in the UAE and GCC

Regional flow modelling has strong published anchor points and specific structural features.

Calibration should rest on measured flows: weighbridge records, manifest data and reported diversion. Reported outcomes suitable for calibration include Dubai’s 62 per cent landfill diversion by February 2026, against 20 to 30 per cent before the Warsan facility (up to 6,000 tonnes per day) was commissioned [5]. Planned design capacities and targets are scenario and capacity inputs, not calibration data. These include Abu Dhabi’s greenfield recovery facility at 400,000 tonnes per year, split 200,000 municipal and 200,000 commercial and industrial [2]; Tadweer’s expectation of 15 to 20 per cent recovery from highly automated facilities and the 80 per cent landfill diversion target for 2031 [4]; and Abu Dhabi’s first waste-to-energy plant at 900,000 tonnes per year generating 80 MW from 2027 [9].

Three structural features affect model construction here.

The commercial and industrial fraction is proportionally large and less well characterised than the municipal fraction. A model treating C&I as a single undifferentiated flow will not support recovery facility design, given that Abu Dhabi’s facility is split evenly between the two streams [2].

Construction and demolition waste dominates total arisings regionally and is frequently excluded from municipal models. Whether it sits inside or outside the boundary must be stated, because its inclusion transforms every percentage.

Composition is changing under policy intervention. The two-bin household segregation pilot in Shakhbout City [4] alters residual composition, which means a model calibrated on pre-pilot data will misstate the residual stream after rollout. Models supporting long-lived assets should represent the composition trajectory rather than a static composition.

The regulatory framework supports data availability. Article 23 provides for a national waste database and Article 4 requires competent authorities to prepare waste management plans [6], while Bolisaty and the GPS tracking requirement generate consignment-level movement data.



Frequently asked questions

What is mass balance in waste modelling? Inputs equal outputs plus accumulation for any defined boundary and period, so every tonne must resolve to a destination including residues and losses.

Why do Sankey diagrams matter? Band width is proportional to tonnage and splits must sum to their parent, so an unbalanced model produces a diagram that visibly fails to reconcile.

What recovery rate should a model use? System-level achieved rates, not stage efficiencies. Tadweer expects 15 to 20 per cent recovery from highly automated facilities [4], well below individual equipment figures [3].

Why is generation the weakest number? Facilities measure receipts, not generation, so generation is usually inferred from disposal plus estimated diversion, which makes it a derived rather than independent quantity.

What is the most common modelling error? Omitting residues. Mass burn alone produces bottom ash at 20 to 25 per cent of input plus air pollution control residues, both requiring destinations [5].


References

Show all 9 sources
  1. ASTM D5231-92 (2016). Standard Test Method for Determination of the Composition of Unprocessed Municipal Solid Waste. Accessed: 7 September 2026.
  2. Utilities Middle East. Tadweer awards Abu Dhabi waste recovery facility contract to Urbaser. July 2026. Accessed: 7 September 2026.
  3. Waste Technology UK. Best Automatic Waste Sorting Machine Models and Options: comparative separation performance. February 2026. Accessed: 7 September 2026.
  4. The National. Abu Dhabi to significantly cut landfill use in sweeping waste overhaul. 17 July 2026. Accessed: 7 September 2026.
  5. Dubai Waste. Dubai Waste-to-Energy 2026: Warsan plant capacity, diversion rate and residues. 28 February 2026. Accessed: 7 September 2026.
  6. UAE Federal Law No. 12 of 2018 on Integrated Waste Management, Articles 4 and 23, and Implementing Regulation 2021. Accessed: 7 September 2026.
  7. AI Sorting Machine. A Comprehensive Guide to Selecting Waste Sorting Machines for Mixed Plastic Recycling: preprocessing effect on sorting precision. Accessed: 7 September 2026.
  8. IOP Science. Mastering waste characterisation: seasonal and spatial variation in composition. May 2026. Accessed: 7 September 2026.
  9. Khaleej Times. Abu Dhabi’s new waste-to-electricity plant to power 52,000 homes. 15 April 2026. Accessed: 7 September 2026.

About this article

Charmaine Frost is a landfill gas and waste-management specialist and a founding director of Qualifrost FZC LLC. Her experience was gained with major UK waste-management companies, covering landfill gas generation and collection systems, environmental monitoring and the practical risks of landfill operations. She holds the NEBOSH International General Certificate and has submitted her final NEBOSH Diploma assessment, with results expected in March–April 2027.

Reviewed by Adrian Frost, Director. Articles are checked against primary sources where these are available: legal claims are verified against the instrument itself, and figures against the original dataset where accessible. Where only secondary sources (press or industry publications) are cited, figures should be verified against the primary source before being relied upon.

Published 25 August 2026 · Last reviewed 7 September 2026 · Next review August 2027, or sooner if the law changes.