Detailed Design and Engineering: Basis of Design, PFDs, P&IDs and Disciplines
Detailed design converts a feasibility conclusion into documents a contractor can build from. This guide covers the basis of design that governs everything downstream, the process documentation hierarchy from block diagram to P&ID, the engineering disciplines and their interfaces, and where design errors actually originate.
By Charmaine Frost, Director and Landfill Gas Specialist

In short
Detailed design translates a defined concept into construction documentation. It begins with a basis of design fixing design capacity, feedstock specification, output specification, site conditions and applicable codes. Process documentation develops through block flow diagram, process flow diagram and piping and instrumentation diagram, each adding detail without contradicting the last. Disciplines comprise process, civil, structural, mechanical, electrical, instrumentation and control. The most consequential input is feedstock specification, since achieved recovery of 15 to 20 per cent from automated facilities [1] differs sharply from stage efficiencies of 85 to 99 per cent [2].
Key facts
- The basis of design fixes design capacity, feedstock specification and variability, output specification, site conditions and applicable codes before any drawing is produced, with arid drainage sized against event rather than annual average rainfall [9].
- Feedstock specification must reflect measured composition from characterisation under ASTM D5231-92, including seasonal and spatial variation [3].
- Design recovery assumptions should use system rates, with Tadweer expecting 15 to 20 per cent recovery from highly automated facilities [1], not equipment stage efficiencies of 85 to 99 per cent [2].
- Inadequate feedstock preprocessing reduces sorting precision by as much as 15 to 20 per cent, so preparation stages must be designed to the specification the downstream stage requires [4].
- Combustion design must satisfy regulatory conditions of gas residence at minimum temperature after the last combustion air injection, typically 850 degrees Celsius for two seconds rising to 1,100 degrees for high halogen content [5].
- Secondary combustion chamber volume is designed on gas residence time of at least 2 seconds with cross-sectional velocity controlled at 3 to 8 metres per second [6].
- Refractory for corrosive flue gas must be corrosion-resistant magnesia-chrome or silicon carbide, with external shell temperature at or below 50 degrees Celsius [6].
- Structural design for waste handling requires reinforced concrete tipping floors and push walls designed for repeated loader impact, with clear-span construction avoiding internal columns [7].
Plain English — the essentials, in everyday language
Plain English
What detailed design produces
Detailed design turns a decision into buildable documents.
At the end of it a contractor should be able to price the work accurately, build it without having to invent anything, and have it work when commissioned.
That means drawings, specifications, calculations, schedules and data sheets, all consistent with each other.
The basis of design comes first
Everything else depends on this document, and it is worth getting slow and right.
The basis of design fixes design capacity, what the feedstock is and how much it varies, what the outputs must achieve, site conditions, applicable codes and standards, and the design life.
Change any of these later and the redesign cost compounds through every discipline.
Feedstock is the critical input
The single most consequential number in the basis of design is what the plant will receive.
That comes from characterisation under ASTM D5231-92, including seasonal and spatial variation [3], not from a generic composition table.
A plant designed for a composition it does not receive will underperform permanently, and no amount of operating skill fixes it.
Design for the range, not the average
A related discipline. Composition varies, and design should reflect the range.
Design for the average and the plant fails at the extremes. Design for the worst case throughout and it is unaffordably oversized.
The judgement is which parameters need worst-case design and which can be averaged, and that depends on which failures are recoverable.
The document hierarchy
Process documentation develops in three stages, each adding detail.
A block flow diagram shows major process blocks and the main streams between them. It fits on one page and establishes the concept.
A process flow diagram adds equipment, main lines, operating conditions and a mass and energy balance. This is what the process is.
A piping and instrumentation diagram adds every line, valve, instrument and control loop. This is what gets built.
Each must be consistent with the one before. An inconsistency between PFD and P&ID is a design error waiting to become a construction claim.
The disciplines
Process engineering defines what happens and sizes the equipment.
Civil covers earthworks, drainage, roads, foundations and containment.
Structural covers buildings, supports and the loadings imposed by waste handling.
Mechanical covers equipment, piping, ventilation and cranes.
Electrical covers supply, distribution, motors and lighting.
Instrumentation and control covers measurement, control loops, the control system and safety systems.
Interfaces are where errors live
Most design errors are not within a discipline. They are between disciplines.
A pipe routed through a beam. A motor requiring more power than the electrical design allows. A foundation that does not match the equipment base plate. An instrument with no access for calibration.
Interface management, meaning formal exchange of information between disciplines with sign-off, is what prevents these.
Waste-specific structural demands
Waste handling is unusually hard on structures.
Tipping floors need reinforced concrete resisting abrasion from waste and loader buckets, and push walls must be designed for repeated loader impact rather than incidental contact [7].
Clear-span construction removes internal columns that collect waste, obstruct loaders and become damage points [7].
Floors need positive slope to drainage, no crevices or flat ledges where waste lodges, and discharge to an enclosed tank or foul sewer rather than surface water [7].
Thermal design constraints
For thermal plant, regulation fixes some design parameters directly.
Combustion must hold flue gas at a minimum temperature after the last combustion air injection, typically 850 degrees Celsius for two seconds, rising to 1,100 degrees where halogenated content is high [5].
Secondary chamber volume is sized on that residence time, with cross-sectional velocity controlled at 3 to 8 metres per second for turbulent mixing [6].
Refractory must resist the corrosive gas, using magnesia-chrome or silicon carbide, with the outer shell insulated to 50 degrees Celsius or below [6].
Designing for operation
A plant that works on paper and cannot be maintained is a failed design.
Access for maintenance, lifting provision for heavy components, isolation for safe working, spares commonality, and washdown provision all belong in design rather than being discovered in operation.
Involving the intended operator in design review is the most effective single control.
Design for the climate here
High ambient temperature affects equipment derating, cooling capacity and control room loads.
Dust affects filtration, bearing protection and enclosure ratings.
Ground conditions including sabkha and gypsiferous soils affect foundations and buried services.
Corrosivity from chloride affects concrete cover, coatings and material selection.
Professional layer — engineering, operations & compliance detail (click to expand)
Professional
Basis of design
The basis of design is the governing document from which all subsequent engineering derives, and its quality determines the quality of everything downstream.
Content comprises design capacity, stated as annual throughput, design hourly rate and the turndown range across which the plant must operate; feedstock specification including composition with variability, moisture, bulk density, particle size distribution, calorific value where relevant and contaminant limits; output specification for each product and residue stream; performance guarantees to be demonstrated at commissioning; site conditions covering geotechnical, hydrogeological, meteorological and seismic parameters; utility availability and quality; applicable codes, standards and regulatory requirements; design life and availability target; and interface definitions with existing or third-party infrastructure.
Two disciplines separate a robust basis of design from a nominal one.
Every parameter carries a source. Measured, calculated, benchmarked or assumed, stated explicitly, so that a reviewer can identify which figures carry risk.
Ranges rather than points where the parameter varies. Feedstock composition, ambient temperature and throughput all vary, and the design case for each parameter must be selected deliberately.
Change control applies from issue. Once approved, revision requires formal assessment of consequences across disciplines, because a late change to a basis of design parameter propagates through every discipline that used it.
Feedstock specification
Feedstock specification is the input most likely to be wrong and most damaging when it is.
It should derive from characterisation conducted under ASTM D5231-92, reapproved 2016, with sample numbers set by statistical criteria and load selection randomised over a five to seven day period [3]. Where seasonal and spatial variation exists, a single sampling period is insufficient to characterise either dimension [8], so the specification should state the composition range across the design envelope rather than a single figure.
Design case selection follows from consequence. Parameters where the failure mode is unrecoverable, such as combustion temperature at minimum calorific value, are designed to the adverse extreme. Parameters where the failure mode is a recoverable performance shortfall may be designed nearer the mean.
Recovery assumptions require the same discipline. Published stage efficiencies of 85 to 90 per cent for ballistic separation, 95 to 99 per cent for magnetic separation, 90 to 95 per cent for eddy current and 92 to 98 per cent for near-infrared optical sorting [2] apply to prepared feedstock at specified burden depth. System recovery from municipal waste is far lower, with Tadweer expecting 15 to 20 per cent recovery from highly automated facilities [1].
Preprocessing specification connects the two. Inadequate preprocessing reduces sorting precision by as much as 15 to 20 per cent [4], and fragments sized between 10 and 50 mm give near-infrared and AI systems a consistent scanning surface [4]. Where the design relies on a downstream stage achieving its rated performance, the preparation stages must be specified to deliver the feed condition that rating assumes.
Process documentation hierarchy
Process documentation develops progressively, each level adding detail while remaining consistent with those above it.
The block flow diagram presents major process blocks and principal streams, establishing the concept on a single sheet and forming the basis of the mass balance.
The process flow diagram presents major equipment with tag numbers, main process lines, operating conditions of temperature, pressure and flow, and the mass and energy balance. It defines what the process does and is the reference document for process performance.
The piping and instrumentation diagram presents all piping with line numbers, sizes, specifications and insulation; all valves including type and function; all instruments with tag numbers and functions; all control loops; equipment with nozzles and connections; safety devices including relief valves and rupture discs; and utility connections. It is the primary reference for construction, commissioning and operation, and it remains the operating document for the life of the plant.
Supporting documentation comprises equipment lists and data sheets, line lists, instrument indices, cause and effect matrices, control narratives, hazardous area classification drawings and single line diagrams.
Consistency between levels is a formal check rather than an assumption. Discrepancy between PFD and P&ID is among the most common sources of construction-stage query and claim.
Engineering disciplines
Seven disciplines contribute, each with defined outputs.
Process engineering establishes the flow scheme, sizes equipment, produces the mass and energy balance, specifies operating conditions and writes control philosophy.
Civil engineering covers site levels and earthworks, roads and hardstanding, surface water drainage and attenuation, containment and bunding, and foundations. In arid settings, drainage must be sized against intense short-duration rainfall events rather than annual average, since those events can generate volumes far exceeding steady-state design capacity [9].
Structural engineering covers buildings, equipment support structures, access platforms and the specific loadings imposed by waste handling.
Mechanical engineering covers rotating and static equipment specification, piping design and stress analysis, ventilation and odour control, and lifting equipment.
Electrical engineering covers incoming supply and transformation, distribution and switchgear, motor control centres, emergency power, earthing and lightning protection, and lighting.
Instrumentation and control covers field instrumentation, control system architecture, control loops and interlocks, safety instrumented systems, and continuous emissions monitoring where required.
Specialist inputs include fire engineering, acoustics, odour dispersion modelling and hazardous area classification.
Interface management
Design errors originate predominantly at discipline interfaces rather than within disciplines.
Recurrent interface failures include spatial clashes between structure, piping, cable routes and ductwork; load information not transferred from mechanical to structural in time to influence foundation design; electrical demand exceeding the design allowance because equipment selection changed; instrument locations without access for calibration or removal; and drainage points not coordinated with equipment layout.
Control mechanisms are formal interface registers identifying each information exchange with originator, recipient and required date; three-dimensional model coordination with scheduled clash detection; design review at defined completion percentages with all disciplines present; and hold points preventing progression until interface information is confirmed.
Interface management effort scales with project complexity and is consistently underestimated in design fee budgets.
Waste-specific design requirements
Waste facilities impose demands that general industrial design does not anticipate.
Structural requirements for waste handling areas are severe. Reinforced concrete tipping floors must resist abrasion from both waste and loader buckets, and concrete push walls must be designed for repeated loader impact rather than incidental contact [7]. Clear-span construction removes internal columns that collect waste, obstruct loaders and become damage points, and building geometry should avoid recesses and horizontal ledges where waste lodges [7].
Drainage requires positive slope to collection points, elimination of crevices, corners and flat surfaces, and discharge to an enclosed holding tank or foul sewer rather than surface water [7].
Odour containment requires design measures rather than operational compensation: building orientation with respect to prevailing wind and sensitive receptors, two-door vestibules in which the outer door closes before the inner opens, plastic strip curtains at openings, and treatment by biofilter or misting with neutralisers [10].
Combustion design for thermal facilities is partly fixed by regulation. Gas residence at minimum temperature after the last injection of combustion air is typically 850 degrees Celsius for two seconds, rising to 1,100 degrees where halogenated organic content exceeds defined thresholds [5]. Secondary combustion chamber volume is designed on gas residence time of at least 2 seconds with cross-sectional velocity controlled at 3 to 8 metres per second to ensure turbulent mixing [6].
Materials selection for corrosive service is specified rather than defaulted. Refractory for hydrogen chloride and sulphur oxide service must be corrosion-resistant magnesia-chrome or silicon carbide, with the metal shell insulated to maintain external wall temperature at or below 50 degrees Celsius [6].
Wear component design should assume replacement. Ballistic separator paddles are specified as replaceable [11], and wear parts across the plant should be accessible and standardised.
Design for operability and maintainability
A design that cannot be operated and maintained economically has failed regardless of its process performance.
Requirements include access for routine inspection and maintenance without confined space entry where avoidable; lifting provision, whether crane, hoist or davit, for every component too heavy to handle manually; isolation provision for safe working, both process and electrical, designed in rather than improvised; standardisation of equipment types to reduce spares holding and training burden; washdown provision with drainage in all waste handling areas; and adequate laydown space for maintenance activity.
Redundancy decisions should follow availability targets and consequence of failure rather than convention. Where a single equipment failure stops the plant, and the plant has a contractual availability obligation, redundancy is an economic decision rather than a technical preference.
Operator involvement in design review is the single most effective control on operability defects, and it should occur at concept and at detailed stages rather than at handover.
Design review and verification
Formal review at defined stages provides the assurance that documentation is correct and complete.
Review types include process hazard review, commonly HAZOP conducted on completed P&IDs; constructability review with contractor input; operability and maintainability review with operator input; interdisciplinary clash review on the coordinated model; and compliance review against the basis of design and applicable standards.
Independent verification of critical calculations, particularly structural and containment design, is appropriate where failure consequence is high.
Design freeze at a defined point is necessary. Continuing change through construction is the principal cause of cost growth and programme delay, and the discipline of a formal freeze with change control thereafter is worth the inflexibility it imposes.
Application in the UAE and GCC
Regional conditions impose design requirements that temperate reference designs do not address.
Thermal design conditions require equipment derating at high ambient temperature, increased cooling capacity for control rooms and switchrooms, and consideration of thermal expansion ranges wider than temperate practice assumes. Oxygen solubility falls with temperature, increasing aeration demand in biological processes.
Dust ingress requires higher enclosure protection ratings, filtration on ventilation intakes and bearing protection on outdoor rotating equipment.
Ground conditions frequently include sabkha with low bearing capacity, high compressibility and aggressive groundwater chemistry, and gypsiferous soils subject to dissolution and collapse on wetting. Both require identification at desk study stage and both determine foundation design and buried services specification.
Chloride and sulphate aggressivity determines concrete mix design, cover to reinforcement, coating specification and material selection for buried and submerged elements.
Rainfall design uses event rather than annual average, since intense short-duration events can generate volumes far exceeding steady-state capacity [9].
Regulatory design parameters follow the emirate. Emission standards at Warsan meet EU Industrial Emissions Directive 2010/75/EU limits with continuous monitoring published on public dashboards [12], which establishes the regional benchmark. Under UAE Federal Law No. 12 of 2018, Article 9 provides for landfill requirements through the Implementing Regulation, Article 11 requires source separation through uniform colour-coded containers [13]. Detailed design obligations should be verified against the text of Cabinet Resolution No. 39 of 2021 on the Implementing Regulation of Federal Law No. 12 of 2018.
Design capacity should reflect the composition trajectory rather than current composition, since Abu Dhabi’s two-bin household segregation pilot will alter residual composition over the design life [1], and a plant designed only for present composition will be mismatched to its feed within a few years of commissioning.
Frequently asked questions
What is the basis of design? The governing document fixing capacity, feedstock, outputs, site conditions, codes and design life, from which all subsequent engineering derives.
What is the difference between a PFD and a P&ID? A PFD shows major equipment, main lines and operating conditions with the mass and energy balance. A P&ID shows every line, valve, instrument and control loop and is what gets built.
Which design input causes most problems? Feedstock specification. A plant designed for composition it does not receive underperforms permanently, which is why characterisation must cover seasonal and spatial variation [3][8].
Where do design errors originate? Predominantly at discipline interfaces rather than within disciplines, which is why formal interface registers and clash detection matter.
What is different about designing waste handling structures? Tipping floors must resist loader and waste abrasion, push walls must take repeated loader impact, and clear-span construction avoids columns that collect waste and obstruct plant [7].
References
Show all 13 sources
- The National. Abu Dhabi to significantly cut landfill use in sweeping waste overhaul. 17 July 2026. Accessed: 7 September 2026.
- Waste Technology UK. Best Automatic Waste Sorting Machine Models and Options: comparative separation performance. February 2026. Accessed: 7 September 2026.
- ASTM D5231-92 (2016). Standard Test Method for Determination of the Composition of Unprocessed Municipal Solid Waste. Accessed: 7 September 2026.
- AI Sorting Machine. A Comprehensive Guide to Selecting Waste Sorting Machines: preprocessing effect on sorting precision and particle size. Accessed: 7 September 2026.
- Dubai Waste. Dubai Waste-to-Energy 2026: Warsan combustion and emission control configuration. 28 February 2026. Accessed: 7 September 2026.
- Cementl. Hazardous Medical Waste Incineration Plant Rotary Kiln: secondary combustion chamber design, velocity and refractory specification. July 2025. Accessed: 7 September 2026.
- Waste Today Magazine and Waste360. Transfer station structural design: tipping floors, push walls, clear-span construction and drainage. Accessed: 7 September 2026.
- IOP Science. Mastering waste characterisation: seasonal and spatial variation limitations. May 2026. Accessed: 7 September 2026.
- Landfill Gas Methane Calculator and arid climate design guidance: rainfall event sizing. March 2026. Accessed: 7 September 2026.
- US EPA. Waste Transfer Stations: A Manual for Decision-Making: odour containment design measures. Accessed: 7 September 2026.
- MechWaste. Ballistic Separator specifications: replaceable wear paddles and deck configuration. May 2026. Accessed: 7 September 2026.
- Dubai Waste. Warsan emission monitoring against EU IED 2010/75/EU limits. 28 February 2026. Accessed: 7 September 2026.
- UAE Federal Law No. 12 of 2018 on Integrated Waste Management, Articles 9 and 11, and Cabinet Resolution No. 39 of 2021 on the Implementing Regulation of Federal Law No. 12 of 2018. Accessed: 7 September 2026.
Related articles
- Construction supervision
- Feasibility studies
- Procurement and contracting models
- Operations and maintenance planning
- Facility siting criteria
- Material recovery facilities
- Mass burn incineration
- Emission control technologies
- Waste management in the Gulf context
About this article
Charmaine Frost is a landfill gas and waste-management specialist and a founding director of Qualifrost FZC LLC. Her experience was gained with major UK waste-management companies, covering landfill gas generation and collection systems, environmental monitoring and the practical risks of landfill operations. She holds the NEBOSH International General Certificate and has submitted her final NEBOSH Diploma assessment, with results expected in March–April 2027.
Reviewed by Adrian Frost, Director. Every article is checked against primary sources before publication: legal claims are verified against the instrument itself, and figures against the original dataset.
Published 25 August 2026 · Last reviewed 25 August 2026 · Next review August 2027, or sooner if the law changes.